If your property is in unincorporated Los Angeles County, your building permit is not one approval. Public Works Building and Safety issues it. But it issues only after every agency on its Agency Referral sheet has signed off. That can mean:

  • the Fire Department;
  • your water company;
  • the Sanitation Districts;
  • Regional Planning;
  • the County’s geology and soils reviewers;
  • Public Health;
  • your school district;
  • the County Library.

Each has its own queue, forms and fees.

The County’s own referral sheet puts it plainly: "Follow-up is your responsibility."

This page walks through every agency you may meet, what each one checks, and where projects lose months. It closes with seven County projects from our own files.

On this page: Is it County? · How a permit moves · The agencies · ADUs and state law · Seven real projects · Where months go · How we run a County project · FAQ

Three things owners mix up
  1. A Regional Planning approval is not a permit. It settles zoning. Fire flow, septic, geology, drainage and the fees are all still open.
  2. Water service is not fire flow. A working meter tells you nothing about what the nearest hydrant can deliver. Fire needs the hydrant numbers, and they come from your water company.
  3. A fee on the referral sheet is not always a fee owed. Some projects are exempt by law. Even so, the agency still has to issue a certificate of clearance before the permit can issue.

01. Is your property in unincorporated LA County?

Your mailing address does not tell you. Our own County projects include homes with Pasadena, Calabasas, Malibu, Inglewood, Hawthorne and Whittier mailing addresses. In each case the County handles zoning, plan check and permits, not the city on the envelope.

Unincorporated areas include:

  • Altadena, East Los Angeles, Hacienda Heights and Rowland Heights;
  • Topanga and the Santa Monica Mountains;
  • Acton, Agua Dulce and much of the Antelope Valley;
  • dozens of smaller communities.

Two ways to check:

  • Public Works service locator. Look up the address at dpw.lacounty.gov/general/servicelocator. It also shows your water company and school district.
  • Regional Planning zoning map. It shows the zone and any Community Standards District.

Some cities contract with the County for building plan check. Their projects get a County referral sheet too, but zoning stays with the city.

02. How a County permit moves

  1. Zoning review by Regional Planning.
    • Most projects need a Regional Planning approval before the building permit can issue. It is filed as a sub-record of your building application in EPIC-LA, the County’s online permit system.
    • Regional Planning checks the zone, setbacks, height, lot coverage and parking. It also checks any overlay that applies. Examples:
      • a Community Standards District;
      • a hillside area;
      • a Significant Ecological Area;
      • oak trees;
      • the coastal zone;
      • a fire recovery area.
  2. Building plan check by Public Works.
    • A plan check engineer at the district office reviews the structure, energy, plumbing, mechanical, electrical and green building sheets.
  3. The Agency Referral sheet.
    • Early in plan check, the engineer marks the agencies your project needs. The header flags the conditions that drive most of them:
      • Very High Fire Hazard Severity Zone
      • sewer or septic
      • highway dedication
      • geology
      • methane
      • open code enforcement
      • whether a new address is needed
    • The sheet also warns that more clearances may be added later in plan check.
  4. Each agency reviews on its own.
    • You submit plans, reports and forms directly to each one, on its own schedule.
    • You don’t have to wait for the agencies. The County lets building plan check start before the agency approvals are in, so the two run side by side. That saves time. The trade-off: when an agency comment moves a wall or adds sprinklers, the revised sheets go back through plan check, which can add time and plan check fees.
  5. Fees and certificates.
    • School, library, sewer and other fees are paid to each agency, not to Building and Safety.
    • You bring back the proof: a certificate of payment, or a certificate of clearance if the project is exempt.
  6. All approvals in, then the permit.
    • Every agency approval has to reach Building and Safety at least 48 hours before the permit can issue.
    • Deferred items. An agency may agree to let one item, such as the fire sprinkler plans, follow after the permit. The requirement doesn’t go away. It gets a later deadline, and it has to be met before the job is signed off.

Dates to watch:

  • The review clock pauses. Under Government Code 65913.3, when another agency’s approval is required, the County’s time limits for reviewing your application stop running until you hand Building and Safety that approval. The referral sheet itself serves as the notice.
  • Applications expire.
    • A County building application expires one year after you apply if no permit has issued (Title 26, Section 106.4.1.1).
    • The County can grant up to two extensions of up to 180 days each. You have to request them in writing, show that the delay was beyond your control, and pay a fee.
    • After that, you file a new application, resubmit the plans and pay plan check again.
  • Fire approvals expire too. A Fire Department plan approval expires one year after Fire approves it if the building permit hasn’t issued by then. Up to two six-month extensions are allowed (Title 32, Section 106.2.4.2).
  • Permits expire after issuance. An issued permit expires if work doesn’t start within 12 months, or if work stops for 180 days (Title 26, Section 106.5.4).

03. The agencies, one by one

Not every project needs all of these. A typical ADU or addition needs four to eight. A rural or hillside site can need a dozen.

  • Building and Safety, Grading and Drainage.
    • Drainage review for new buildings and additions, including stormwater and Low Impact Development (LID) requirements. LID features may need a recorded covenant.
    • Grading plan check on hillside sites (slope of 25 percent or more), larger disturbed areas, or sites next to sensitive habitat. These need a rough grade approval before the building permit.
    • A drainage review is not a grading permit. Check which one your sheet asks for before you pay for a full grading plan.
  • Geotechnical and Materials Engineering Division (GMED). The County’s geology and soils reviewers. GMED reviews:
    • sites in a mapped seismic hazard zone (liquefaction or earthquake-induced landslide) or near a fault;
    • steep or unstable slopes and debris flow areas;
    • retaining walls, basements and deep foundations;
    • shoring and temporary excavations.

    A flat lot can still land here if it sits in a liquefaction zone. GMED approves the geology and soils reports before the building permit issues. Your soils engineer writes the report. GMED’s review is a separate step, and its comments can send the report back for another round.

  • Environmental Programs.
    • Construction and demolition debris. Many projects need a Recycling and Reuse Plan, filed on EPIC-LA, with a refundable deposit. One went onto the referral sheet for a patio enclosure of 209 square feet.
      • Since August 19, 2024, at least 70 percent of mixed debris, and all soil hauled off site, must be recycled or reused.
      • At the end of the job, the hauler’s weight tickets go into a Final Compliance Report. It has to be approved before the County’s final sign-off and occupancy, and it is how the deposit comes back.
      • Agree with your contractor up front on who keeps the weight tickets.
    • Methane. Review for sites within 1,000 feet of a landfill or near oil wells.
  • Land Development.
    • A landscape water efficiency plan when new or rebuilt landscaping exceeds 500 square feet.
    • Highway dedication and street improvements where the County needs more right-of-way along your frontage.
    • Bridge and Major Thoroughfare fees in designated areas.
  • Road permits. A separate permit for a new driveway approach, curb cut or any work in the County road or a flood control easement.
  • Waterworks Districts. Where the County itself is the water provider, for example the Malibu and Antelope Valley districts. A "will serve" letter is required for any new dwelling unit.
  • Mapping and Property Management. A new address before permit issuance, for a new house, or for an ADU with its own electric meter or its own driveway.
  • Aviation. Review for sites near County airports.
  • Fire Prevention Engineering. Access, water supply, hydrants and sprinklers. For ADUs, the Fire Department’s own guideline (EG-07) sets:
    • Hydrant distance: a hydrant within 450 feet of the frontage by road (750 feet where there is less than one home per acre).
    • Hose reach: every part of the ADU within 150 feet of an approved access road. A detached ADU with sprinklers can extend this to 300 feet.
    • Water flow: at least 1,000 gallons per minute for one hour without sprinklers, or 500 gallons per minute for half an hour with them. In a fire hazard severity zone, at least 1,250 gallons per minute for one hour.
  • Fire flow form. Your water company fills out a fire flow availability form (Form 195 or 196) showing what the nearest hydrant can deliver. If it falls short, Fire may require sprinklers, a new hydrant, or both.
    • State law does not require sprinklers in an ADU when the main house is not required to have them.
    • Even so, sprinklers are often how Fire lets a short-flow site go forward.
  • Fire sprinkler plans. Where sprinklers are required, they are a separate Fire submittal, and they are often the item Fire allows to follow after the permit.
  • Fuel Modification. In a Very High Fire Hazard Severity Zone, you need a fuel modification plan approved by the Fire Department’s Fuel Modification Unit. It sets what can be planted, and what has to be cleared, within set distances of the structure. Settle it before the landscape design is final, especially where oaks or protected habitat are nearby.
  • Fire station fee. Charged in certain areas of the County before the permit issues.
  • Zoning approval for the project, filed through EPIC-LA.
  • Overlays that add review:
    • Community Standards Districts (Altadena has its own);
    • hillside management areas;
    • Significant Ecological Areas;
    • oak tree permits, both for removing a protected oak and for grading, trenching or paving within its protected zone;
    • the Santa Monica Mountains coastal zone.
  • Fire recovery. For Eaton Fire properties, the disaster recovery permit and the like-for-like rules in Title 22, Chapter 22.258.
  • Your water company. The service locator tells you who it is. In Altadena alone, five water providers serve different streets:
    • Las Flores Water Company
    • Lincoln Avenue Water Company
    • Rubio Cañon Land and Water Association
    • Kinneloa Irrigation District
    • Pasadena Water and Power

    The water company provides:

    • the "will serve" letter for new units;
    • the fire flow form;
    • meter upgrades when the new unit needs more water service.

    The County’s referral sheet advises checking will-serve and fire flow requirements with your water company in advance.

  • County Sanitation Districts. A sewer connection fee when the project adds a unit or increases use.
    • State law limits what can be charged for an ADU, see section 04.
    • Their connection fee application has its own box for ADUs. It also offers a demolition credit and a change-in-use credit. To get either credit, send proof with the application, such as the demolition permit or the original plans.
  • No sewer? See Public Health below.
  • Septic. Where there is no sewer, Environmental Health reviews the private sewage disposal system: soil testing, system design and capacity for the added bedrooms.
    • The tank, the disposal field and its reserve area can decide where the house can go.
    • The bedroom count drives the system size. Two of the projects in section 05 turned on exactly that.
  • Wells. A water supply approval where the site is served by a well instead of a water system.
  • Recorded covenants. A covenant may need to be recorded for the sewage disposal system.

These are paid to each agency, not to Building and Safety. We don’t list amounts on this page: they change every year and vary by district.

  • School district. Your school district collects a fee on new residential square footage.
    • The district follows the address, not the city name. Altadena projects pay Pasadena Unified, and Topanga projects pay Los Angeles Unified.
    • Some areas have a separate elementary district and high school district, so one project pays two. An Antelope Valley ADU of ours did.
    • The order matters. For Los Angeles Unified:
      1. Building and Safety certifies the new square footage on the district’s form. The district won’t take payment until it does.
      2. You pay the district.
      3. You bring the countersigned form and the receipt back to Building and Safety.
  • County Library. A library facilities fee on new dwelling units in unincorporated areas (Title 22, Chapter 22.264). A single house built by its owner, and additions that do not add a unit, are exempt. Even exempt projects need the Library’s certificate of clearance before the permit issues.
  • Sanitation Districts connection fee.
  • Bridge and Major Thoroughfare fee in designated areas.
  • Fire station fee in designated areas.
  • Caltrans. For driveways, grading or drainage that touch a state highway, such as Topanga Canyon Boulevard, Angeles Crest Highway or Pacific Coast Highway.
  • South Coast AQMD (or the Antelope Valley AQMD). Asbestos notification before demolition or alteration work that disturbs asbestos.
  • Cal/OSHA. A permit for trenches 5 feet or deeper that a worker enters, which often applies to basements and deep foundations.
  • California Division of Oil and Gas. Clearance where an abandoned oil well is on or near the site.
  • County Parks and Recreation. Review for construction next to a designated trail.

Three real referral sheets

  • A covered patio enclosure of 209 square feet, unincorporated area with a Pasadena mailing address.
    • Clearances marked:
      • Regional Planning
      • Land Development (a landscape plan, "if any")
      • a debris recycling plan
    • The plan checker also wrote in the local water company. The sheet’s printed note told every applicant to check will-serve and fire flow requirements with the water company in advance.
  • A hillside ADU in Topanga. Clearances on the sheet:
    • drainage
    • GMED slope stability review (over-steepened slopes, landslide, debris flow)
    • a will-serve letter from Waterworks District 29
    • Fire Prevention
    • fire sprinkler approval
    • Fuel Modification
    • Regional Planning
    • Caltrans
    • a debris recycling plan
    • a new address
    • the Los Angeles Unified school fee
  • A 647 square foot ADU on septic in the Antelope Valley. Clearances marked:
    • Regional Planning
    • drainage
    • GMED
    • a debris recycling plan
    • a new address and proof of ownership
    • Environmental Health (septic)
    • Fire plan approval and building release
    • the fire station fee
    • the water company’s will-serve letter and fire flow form
    • two school districts
    • the County Library

    The sheet also set a 20 psf ground snow load and called for collapse and hydro-consolidation testing in the soils report. The library and fire station fee lines show why a fee referral isn’t a bill: state law bars impact fees on an ADU of 750 square feet or less.

04. ADUs in the County: what state law changes

  • Impact fees. Under Government Code 66311.5 (as in effect January 1, 2026), no impact fees on an ADU of 750 square feet or less, or a junior ADU of 500 square feet or less. Above that, fees must be proportional to the main house.
  • School fees. An ADU or junior ADU under 500 square feet is treated as not adding 500 square feet of assessable space, so the school district fee generally does not apply. Larger units pay.
  • Each fee is its own question. An exemption from impact fees doesn’t settle the school fee, the plan check fee or the utility charges. Check each one.
  • Utility connections. A water or sewer agency cannot treat an ADU as a new residential use for connection fees unless it is built with a new single-family home. Where a separate connection is allowed, the charge has to be proportionate.
  • Sprinklers. Not required in an ADU when the main house is not required to have them, unless they become Fire’s condition for a site with a short hydrant or long access.
  • The 60-day clock covers zoning only.
    • State law gives the County 60 days to act on a complete ADU application. The Fire Department’s own guideline notes that this covers zoning review.
    • Building plan check, Fire review and the other agencies have no set timeline.
    • Their approvals also pause the County’s review clock until they are delivered.
  • Addresses. An ADU needs its own address only when it has its own electric meter or its own driveway.

05. Seven County projects from our files

To protect our clients’ privacy, each project is identified by community and type only.

  • Eaton Fire rebuild with a detached ADU, Altadena (2025).
    • Clearances:
      • Regional Planning
      • drainage
      • the debris recycling plan
      • Fire Prevention Engineering
      • the water company’s will-serve letter
      • Southern California Edison
      • the Sanitation Districts
      • Pasadena Unified school fees on the added floor area
    • Fire allowed the sprinkler plans to follow as a deferred item.
    • Permit cards for both buildings issued about seven weeks after building intake, and about five months after the Planning filing.
  • Hillside ADU, Topanga (filed 2023).
    • Eleven clearances, including GMED, Waterworks District 29, Caltrans, Fuel Modification and the Los Angeles Unified school fee.
    • Fire first asked for 1,250 gallons per minute. The hydrant tested at 750.
    • The Waterworks District and Fire then confirmed that a lower flow requirement applied. The fuel modification plan was released in June 2024, and Fire cleared the project that July.
    • By then the building application had expired, and the County reopened it under a new number in October 2025.
    • The lesson: get the fire flow numbers before design, and watch the expiration date from day one.
  • Garage conversion with a new attached garage, Acton (filed 2020).
    • The new driveway crossed an adjacent lot, so the County asked for an easement or a lot tie.
    • The septic review turned on how many bedrooms the system had to serve.
    • GMED asked for foundation sheets.
    • A Planning amendment was approved in January 2022, GMED cleared in February and Fire in April. The permit issued in May 2022, 20 months after the case opened.
  • Two-story detached ADU, East San Gabriel (filed 2019).
    • Regional Planning could not sign off until the oak tree permit and the County Forestry fees were settled.
    • Fire took further correction rounds.
    • Also on the list: the fire flow form, drainage, the debris plan, school fees and a new address.
    • The permit issued about 19 months after plan check intake.
  • Wildfire rebuild of a two-story home, Santa Monica Mountains (filed 2020).
    • The mailing address says Calabasas. The jurisdiction is the County.
    • Environmental Health was the last sign-off. The septic design had to match the bedroom count.
    • The project also worked through the fire flow form, a fuel modification covenant and several drainage rounds.
    • The fix was fewer bedrooms and revised plans backed by the old septic and debris records.
    • The permit issued 30 months after the case opened.
  • Two-story addition, La Crescenta-Montrose (2017).
    • Regional Planning asked for proof that a 25-foot street dedication had been waived.
    • Public Works issued the approval letter about five months later. Review then moved on to drainage and building revisions.
  • Addition, kitchen remodel and patio cover, Hacienda Heights (2022).
    • In August 2022, Fire asked for the water company’s fire flow form. It came back in December.
    • Building corrections followed in April 2023, and the permit issued that July.
    • A later change to remove a bearing wall needed its own supplemental permit.

How long County permits take in our files.

  • Across 24 County home projects where we have both dates on record, the median was about 6.6 months from filing to permit. The middle half took roughly 4 to 10 months.
  • The fastest took under 2 months from building intake: an Eaton Fire rebuild, which moves on the County’s recovery track.
  • The slowest was the Santa Monica Mountains rebuild above, on septic, at about 30.
  • Size didn’t predict it. The 209 square foot patio enclosure took 10 months from its referral sheet to permit.

Measured from the County case or plan check intake date to permit issuance.

06. Where County projects lose months

  • The referral sheet arrives after the design is done. By then a fire flow shortfall, a liquefaction zone or a septic limit can force a redesign. We read the parcel for these before design starts.
  • Waiting on the water company. Will-serve letters and fire flow forms come from a separate company with its own timeline. In Hacienda Heights the fire flow form alone took four months, and the result can add sprinklers or a hydrant to the project.
  • GMED on a lot that looks flat. A mapped liquefaction or landslide zone triggers a geology and soils review, regardless of how the lot looks from the street.
  • Septic and bedrooms. Adding a bedroom can mean a bigger system, a new disposal field, or a smaller house.
  • Agency comments that change the building plans. A Fire, GMED or Land Development comment often means a revised sheet, which goes back through Building and Safety.
  • Sheets that grow mid-review. The County’s sheet says it plainly: additional clearances may be required by your plan check engineer.
  • The one-year expiration. Long agency queues can push an application toward its expiration date. Extensions cost money, need a written reason, and stop at two. After that you start over with a new application and a new plan check fee.
  • "It’s with the County." That status tells you very little. Ask which agency has it, whether the submittal is complete, and what the next action is.

Budget for four kinds of cost, not one:

  1. Design and permit coordination.
  2. Consultants, as the site needs them:
    • a structural engineer
    • energy compliance
    • a survey
    • a soils engineer
    • a civil engineer
    • a septic designer
    • an arborist
  3. Agency fees: plan check, permit, and the fees on the referral sheet.
  4. What the agencies require you to build:
    • a hydrant or sprinklers
    • drainage devices
    • a septic upgrade
    • retaining walls
    • a driveway approach

A fee to review a soils report doesn’t pay for writing it or revising it.

07. How we run a County project

  • Day one: we read the parcel. Before design, we check:
    • zoning, overlays and any Community Standards District;
    • fire hazard zone, seismic hazard and fault maps, flood zone and methane;
    • sewer or septic, the water company, the school district, and the County Library planning area;
    • frontage and highway dedication;
    • oak trees, trails, and any open code case.

    You get the likely clearance list before you commit to a design.

  • Design for the clearances. Hydrant distance, access, fuel modification and drainage are drawn into the first set, not added after corrections.
  • Submittal management through permit issuance. We file with Building and Safety and each agency, and we track every queue. We coordinate the licensed structural engineer and soils engineer, and we answer agency comments. We also keep the application ahead of its expiration date.
  • Our County record.

What to send us:

  • the address and the Assessor’s Parcel Number (APN);
  • a short description of what you want to build;
  • any existing plans, permits or survey;
  • any referral sheet, correction list or agency letter you already have;
  • soils reports, septic records, water company letters and recorded easements, if you have them;
  • anything you know about slopes, retaining walls, drainage problems, oak trees, a shared driveway, or work done without permits.

Building in unincorporated LA County? Send us the address and any referral sheet you already have. We’ll tell you which agencies your project is likely to need before you spend on design. Call (626) 214-8651.

FAQ

How do I know if my property is in unincorporated LA County?

Look up the address in the Public Works service locator at dpw.lacounty.gov/general/servicelocator. Your mailing city does not decide it. Many Pasadena, Calabasas, Inglewood and Whittier mailing addresses are in unincorporated County communities.

What is an Agency Referral sheet?

It is the form County Building and Safety issues during plan check. It lists every agency that must approve your project before the building permit can issue. Each agency is contacted, paid and cleared separately.

Who is responsible for getting the agency approvals?

The applicant. The County’s referral sheet says “Follow-up is your responsibility.” Every approval must be delivered to Building and Safety at least 48 hours before issuance. We handle this for our clients.

Does a Regional Planning approval mean I can build?

No. It settles zoning. Building plan check and every agency on the referral sheet still have to sign off before the permit issues.

Do small projects need agency clearances?

Often, yes. A 209 square foot patio enclosure of ours needed three: Regional Planning, Land Development and a debris recycling plan. The sheet also named the water company.

Does an ADU in the County pay school and library fees?

Under state law, an ADU under 500 square feet generally does not pay the school district fee, and an ADU of 750 square feet or less pays no impact fees. The Library still requires a certificate of clearance before the permit issues, even when no fee is owed.

My property already has water service. Why does Fire need a water form?

Your water service and fire flow are different questions. Fire needs to know what the nearest hydrant can deliver, and your water company reports it on Form 195 or 196. On one of our Topanga projects, Fire first asked for 1,250 gallons per minute and the hydrant tested at 750.

What if the water company says the hydrant can’t deliver enough flow?

The Fire Department may require fire sprinklers, a new or upgraded hydrant, or both. For an ADU outside a fire hazard zone, Fire’s guideline asks for 1,000 gallons per minute without sprinklers, or 500 with them.

What is GMED, and why does it want a report?

GMED is the County’s Geotechnical and Materials Engineering Division. It reviews geology and soils reports for sites in seismic hazard zones and on slopes. It also reviews reports for retaining walls, basements and deep foundations. Its approval is required before the permit issues.

How long does a County permit take?

There is no single honest number. Zoning review for an ADU has a 60-day state deadline. Building plan check, Fire and the other agencies have no set timeline, and the County’s review clock pauses while their approvals are outstanding. In our own files, the middle half of County home projects took roughly 4 to 10 months from filing to permit. Eaton Fire rebuilds moved faster. Septic, hillside and fire flow sites took longer. The application expires one year after you apply unless the County grants an extension, and it allows two at most.