Eaton Fire Rebuilds
7
In Construction
150
Days to Issued Permits
1,500+
Projects Since 2015
01

Eight rebuilds, seven in construction

Design 1 Studio is designing eight homes lost in the Eaton Fire, seven of them now in construction. One went from building plan-check acceptance to issued permits in 150 calendar days, with a changed footprint, a detached ADU and a regraded site. The work runs from the first County recovery application to the day the permit prints, with a licensed structural engineer coordinated throughout.

02

Like-for-like, and what counts as the same

Los Angeles County’s recovery path lets a lost home be rebuilt as it was, with the same size, location and purpose, under the Zoning Code that applied to the original, while the Building, Fire, and Health and Safety Codes apply as they stand today. In the Eaton Fire area the County allows the rebuilt home to grow by 10 percent of the original floor area or 200 square feet, whichever is greater, and still be treated as like-for-like. Beyond that the current Zoning Code applies. The County sets a 20-foot minimum front setback for every non-like-for-like rebuild in Altadena, and the Altadena Community Standards District’s own front setback rules do not apply to them.

Every area figure has to agree across the plans, the permit descriptions and the planning approval. When they do not, review stops.

03

The County’s rebuild rules, in order

Los Angeles County reviews Eaton Fire rebuilds in unincorporated Altadena on two tracks. A like-for-like rebuild is a structure of the same size, in the same location, for the same purpose as the one lost, with a floor plan that may change and an allowance of 10 percent or 200 square feet, whichever is greater. It does not have to meet the current Zoning Code, though it must meet the current Building, Fire, and Health and Safety Codes. Anything beyond that is a non-like-for-like rebuild, reviewed under the current Zoning Code, with a 20-foot minimum front setback in Altadena and the Altadena Community Standards District’s own front setback rules set aside. The County also publishes pre-approved standard plans for fire rebuilds; a lot that fits one can use it, and a lot that does not is a custom rebuild on one of the two tracks above. The decision between tracks is made on paper before design, from the records of the house that was lost.

Unincorporated LA County projects need sign-offs from several agencies before the permit issues. See how each one works: Unincorporated LA County Permits, Agency by Agency.

04

A changed rebuild through the County in 150 days

Regional Planning cleared the recovery application in July 2025 as a like-for-like rebuild with a detached ADU, and Building and Safety accepted the plans for plan check on September 2, 2025. In October, Building and Safety found that the floor areas in the plans, the permit descriptions and the planning approval did not match. In November the planner cited County Code section 22.04.050, which measures gross floor area from the exterior walls, and offered to process the project as a non-like-for-like rebuild. We brought the planner and the building staff into one exchange, supplied the earlier planning approval, asked for supervisory review, and reworked the grading and the retaining wall. Planning stamped the amended approval in December 2025, and the County issued the building permits on January 30, 2026. The house is in construction.

A scope your adjuster can read

Code-required upgrades are a separate line in our scope: the items the current Building, Fire and energy codes require that the original house did not have. That lets your adjuster apply ordinance-or-law coverage to the right items instead of to a lump sum, and it keeps the design decisions you choose separate from the ones the code imposes.

05

How we run a rebuild

  • The recovery application with Regional Planning, with the original floor area documented from County records, assessor data and any plans that survived.
  • The like-for-like decision made on paper before design: what the family wants against what the 10 percent or 200 square feet allows, and what a changed design costs in review time.
  • The Altadena Community Standards District, the fire hazard zone, hillside rules and any historic overlay read before the first line is drawn.
  • Complete plans, structural coordination, and County plan check managed to issuance, with every area figure reconciled across every document.
  • A detached ADU placed in the rebuild where the lot and the owner’s plans support one.
06

What we need from you

The last permit records or plans for the house, if any survived; the County’s debris-removal clearance; your insurance scope of loss; and a survey if the lot lines are in question. If the records are gone, we rebuild the footprint from the assessor’s record, aerial imagery and the slab, and we document how.

FAQ

FAQ

Can I change the design and still use the recovery path?

Yes, within the 10 percent or 200 square foot allowance in the Eaton Fire area. Beyond it the project is reviewed under the current Zoning Code, which in Altadena means a 20-foot minimum front setback for every non-like-for-like rebuild and sometimes more.

Do the new codes apply to my rebuild?

The Zoning Code that applied to the original home governs a like-for-like rebuild. The current Building, Fire, and Health and Safety Codes apply to every rebuild.

Can I add an ADU?

Yes. Several of our rebuilds include a detached ADU, and the recovery application can carry it.

How long does it take?

Our fastest was 150 days from building plan-check acceptance to issued permits, with planning work before that. Reconciled numbers across the plans, the permit descriptions and the planning approval are what keep a rebuild on that schedule.

Which track should I use?

Like-for-like if the family wants the house back and the 10 percent or 200 square foot allowance covers what they want changed. Non-like-for-like if the footprint, height or use changes beyond that. We put the two side by side on paper first, with the County rules each one triggers, before any design starts.

How we work

A flat fee for the scope, quoted in writing before we start. No hourly surprises.

Plan check corrections are handled through permit issuance as part of that fee.

We draw the plans. We do not build. You own the approved set, and any licensed contractor can bid it.

Every set is coordinated with a licensed structural engineer, and the plans carry our name through the City’s review.

Our rebuilds have run five to eight months from first submittal to permit; the fastest went from building plan-check acceptance to issued permits in 150 calendar days.

Get Started

Start Your Rebuild

Send the address and whatever records of the original house you have. We tell you what like-for-like allows on your lot and what a changed design would take.