A building permit issues only after every reviewer on the project has signed off. This free tracker keeps each approval, each open item and each deadline in one place, so you can see who owes the next action.
The Excel file also opens in Google Sheets. No email needed.
What’s in the file
- Four tabs: unincorporated LA County, the City of Los Angeles, another city, and a blank tab.
- Reviewer rows already listed on the first three tabs. Each starts at “Confirm applicability”, because not every project needs every review.
- Twelve columns, including who has the item now, the next action, your follow-up date and any official deadline.
- A status list on every row: Confirm applicability, Not yet submitted, Submitted, Intake pending, In review, Corrections issued, Resubmitted, Approved, Not required, Ready to issue, Issued.
How to use it
- Start from the official list. In unincorporated LA County, that’s the Agency Referral sheet for your application. In the City of Los Angeles, it’s the LADBS Clearance Summary Worksheet. In another city, it’s the referral or correction sheet. Copy each required review onto its own row.
- Use one row per open item, and copy the reviewer’s wording.
- Record who owes the next action, and any fee, signature or earlier approval it depends on.
- Keep two dates: your own follow-up date, and any official deadline or expiration.
- Update it after every submittal, correction letter and phone call, and note the latest written confirmation.
Two things the tracker is built to catch
- Submitted is not the same as in review. On one of our projects, review hadn’t started because the city had no record of the fee payment.
- Applications and approvals expire. On another, the plans were ready to issue when the reviewer found that the plan check had expired. For the County’s dates, see our LA County agency clearances page.
If your project is stuck
We take over plans already in plan check. Call (626) 214-8651. Serving Los Angeles County and Orange County.
FAQ
Is the tracker free?
Yes. Both files are free, and you don’t need to give an email address.
Do I need Excel?
No. The file also opens in Google Sheets, and there’s a one-page PDF you can print.
Which tab do I use?
Use the first tab for unincorporated LA County, the second for the City of Los Angeles and the third for any other city. Your mailing address doesn’t tell you which one applies. Our LA County agency clearances page explains how to check.
Where do I find the list of required reviews?
In unincorporated LA County, it’s the Agency Referral sheet issued during plan check. In the City of Los Angeles, it’s the LADBS Clearance Summary Worksheet for your application. In other cities, ask for the referral or correction sheet.
Last reviewed: November 2026