City of Los Angeles · Mulholland Specific Plan
Design Review Board Notification Requirements
LAMC §13B.4.3.C (Chapter 1A)
Definition
Notification for a Mulholland Design Review Board hearing is governed by LAMC §13B.4.3.C of Chapter 1A. Two channels are required: a public posting at the project site for at least five days before the hearing, and a mailed notice to all owners and occupants of properties abutting the project lot. The mailing is performed through a mailing vendor approved by the City. Errors or short notice in either channel can void the hearing notice and require rescheduling: at the applicant’s expense and on the applicant’s schedule.
The Notification Components
- 5-day on-site posting at the project site before the DRB hearing date. Photographic documentation of the posting date is part of the packet.
- Mailed notice to all owners and occupants of abutting properties. This is not a 500-foot radial notice; it is the immediately abutting parcels.
- Approved mailing vendor performs the mailing and provides the receipt and signed perjury statement.
- Notification materials (Submittal Material S-6) submitted as part of the DRB packet: vendor receipt, perjury statement, notification map, and mailing labels.
Procedural ReferencePer LAMC §13B.4.3.C: notification to all owners and occupants of properties abutting the subject lot, plus a five-day on-site posting before the hearing.
Notification materials checklist per Mulholland Specific Plan Project Compliance Filing Instructions (CP13-3618), Submittal Material S-6.
What Plan Check Looks For
- A current Notification Map showing all abutting parcels.
- Mailing labels generated from current owner/occupant records.
- A signed perjury statement from the mailing vendor.
- A mailing vendor receipt showing the date the mailing went out, establishing the lead time before the hearing.
- Photographic evidence of the on-site posting at the project site, with a posting date that establishes the 5-day minimum.
- All notification materials submitted as part of the DRB packet at filing, not after.
Upstream Decisions
- Engage a mailing vendor early. Vendor lead time is real, and last-minute mailing errors can void notice.
- Pull abutting-property ownership records from a current title source. Stale records create voids.
- Schedule the on-site posting to provide more than 5 days of notice: give yourself a buffer for late corrections.
- Coordinate the on-site posting with the property owner. The posting must be visible at the property and remain in place through the hearing date.
Worked ExampleA DRB hearing is scheduled for a Wednesday afternoon. The applicant’s mailing vendor sends notice on day −7 (seven days before the hearing). The on-site posting is installed at the property on day −6. Both meet the 5-day minimum.
The packet at submission includes the vendor’s signed perjury statement, the mailing receipt dated day −7, photographs of the on-site posting at days −6, −3, and 0 (hearing day), and the notification map showing all abutting parcels. The hearing proceeds as scheduled. The Board makes a recommendation, which the Director then considers in the formal decision letter issued separately.
Source: Los Angeles Municipal Code §13B.4.3.C (Specific Plan Project Compliance with DRB Procedures, Chapter 1A), public notification requirements. Notification materials checklist per Mulholland Specific Plan Project Compliance Filing Instructions (CP13-3618), Submittal Material S-6.
Working on a property in the Mulholland Specific Plan area?
Design 1 Studio reviews zoning, slope, visibility, grading, and plan check constraints before drawings move too far in the wrong direction.
Building design firm based in Pasadena and Monrovia, California. Serving Los Angeles County and Orange County since 2015 with residential design, including ADUs, hillside projects, and historic-district work. Plan sets are drawn to anticipate plan check rather than react to it. Specialty work in Mulholland Specific Plan navigation. Contact through design1.studio.