An ADU permit in the City of Los Angeles often carries a clearance from the Department of Water and Power, listed on the plan check sheet as “construction within 10 feet of power lines or easement.” For most projects it is a formality. For a building that stands near a pole, it can become a demand to change the building, and in 2026 the Department of Housing and Community Development told LADWP that state ADU law applies to it when it does.
What the clearance is
LADWP reviews ADU applications for access to its poles and lines and can require an encroachment application where a building sits inside the access it wants. In one 2026 case, the legalization of an existing converted garage, the Department rejected the encroachment application and required five feet of clear access to a pole measured from the property line to the outermost part of the building, which would have meant removing part of a building that had stood for decades. The document the Department cited for its right of access was a grant dated September 1923, which its own response described as unrecorded, with the easement width marked N/A. Asked for the written rule behind the five-foot requirement, the Department’s representative wrote that “while the Department may conflict with the stated code,” the access would have to be given.
What state law says
State ADU law defines a permitting agency as any agency involved in the review of an ADU application, including a utility (Government Code section 66313(k)), and holds every permitting agency to the same rules as the city: ministerial review (section 66316), objective standards (section 66313(i)), and the processing requirements of section 66317. A separate provision, section 66311.7, requires a city to approve the legalization of an unpermitted ADU built before 2020 unless it finds a specific condition that endangers health and safety under Health and Safety Code section 17920.3.
What HCD said
On September 25, 2026, HCD’s ADU Policy Section issued a four-page letter of technical assistance to LADWP and the City’s development services chief. The letter addressed the subject matter of 17 complaints among more than 20 HCD had received since 2024, including the case above. It stated that LADWP is a permitting agency under section 66313(k) and must comply with ADU processing requirements including section 66317; that the encroachment requirement “does not appear to be a written standard”; and that it could not tell whether the Department’s process was discretionary, because LADWP refused to provide more information about it to HCD. The letter asked for a written response by October 23, 2026 and noted that if HCD finds a jurisdiction in violation of state law, it may notify the California Office of the Attorney General.
What happened next
Design 1 Studio asked the LADBS plan checker to remove the LADWP clearance from the permit record under the letter; in October, plan check staff said they were not authorized to remove it and pointed to the LADBS bulletin on accessory and junior accessory dwelling units (P/BC 2026-150), which requires LADWP approval where the structure sits in a public utility easement or within 10 feet of one. Whether an unrecorded 1923 grant with no stated width is a public utility easement is a question the record does not answer. LADWP’s representative wrote that the rejected encroachment application “still stands.” LADWP’s management acknowledged the HCD letter and said it was gathering information. As of October 26, 2026, no response from LADWP to HCD’s letter has been made available to the applicant, and the clearance remains on the permit.
What to do if this is your permit
Ask the Department, in writing, for the recorded instrument and the written standard behind the access it wants. Offer access that does not remove housing: a recorded covenant, a keyed gate, the clearance the building already has on another side. Put the request and the answer in front of HCD through its ADU technical assistance portal, which takes complaints against any permitting agency. And do not redraw the building to meet a requirement nobody has shown you in writing.
Source: HCD letter of technical assistance to LADWP, September 25, 2026; Government Code sections 66311.7, 66313, 66316 and 66317; project correspondence, June to October 2026. As read in October 2026; confirm the current text before relying on it.
Trying to figure out what your LA City lot will actually allow?
Design 1 Studio reviews zoning, hillside rules, prevailing setbacks, RFA, and the practical permit pathway for your specific property.
Building design firm based in Pasadena and Monrovia, California. Serving Los Angeles County and Orange County since 2015 with residential design, including ADUs, hillside projects, and historic-district work. Plan sets are drawn to anticipate plan check rather than react to it. Specialty work in LADBS zoning navigation, hillside feasibility, ADU zoning pathways, and residential feasibility reviews. Contact through design1.studio.