City of Los Angeles · Mulholland Specific Plan
Inner Corridor Grading Cap
MSPSP §5 C
Definition
Inner Corridor grading is capped at one cubic yard per four square feet of lot area visible from Mulholland Drive. The Director may approve grading up to two cubic yards per four square feet under the Specific Plan’s discretionary findings procedure, but only after four findings are made. Corrective grading determined by the Department of Building and Safety is excluded from the calculation.
Outer Corridor caps are doubled (default two cubic yards per four square feet; up to four with findings) and live in MSPSP §6 B 1.
The Four Findings for Up to 2:1
Where a project requires more than the default cap, the Director’s findings address:
- Conformance with the City’s Landform Grading Manual, unless Building and Safety determines that landform grading conflicts with Divisions 29 and 70 of Article 1 of Chapter IX of the Code.
- Graded slopes designed to have a natural appearance compatible with the characteristics of the Santa Monica Mountains.
- Building and Safety determination that the grading will minimize erosion.
- Compliance with §10 (Landscaping) on all graded slopes — landform planting where landform grading is not feasible.
What Plan Check Looks For
- Total cut/fill quantities on the Grading Plan (Exhibit E-5) cross-checked against lot area.
- Conformance with the Landform Grading Manual.
- Graded slope appearance compatible with the natural Santa Monica Mountains contour.
- Building and Safety determination that grading minimizes erosion.
- Compliance with §10 landscaping standards on all graded slopes.
Upstream Decisions
- Run grading quantities at the schematic stage. The default cap shapes the building footprint, the foundation strategy, and the driveway alignment.
- Where the project requires more than the default cap, plan the four findings into the Project Description and supporting documentation. Approval is not automatic and the findings must be supported.
- Coordinate landform grading with the Civil Engineer or Land Surveyor preparing the topographic survey. The Slope Band Analysis Form and the Grading Plan must align.
- Treat aesthetics and engineering as parallel reviews. Building and Safety addresses geotechnical safety; the DRB and Director address whether the graded slope appears compatible with the natural contour.
The project is over the default but under the 6,000-cubic-yard with-findings ceiling (12,000 ÷ 4 × 2). The packet supports the four findings: a landform grading scheme per the City’s Landform Grading Manual, transitions to natural slope, planting per §10 on all graded surfaces, and a Building and Safety determination that erosion is minimized. The Director approves the project with conditions, and the grading is permitted at 4,200 cubic yards.
Source: Mulholland Scenic Parkway Specific Plan, §5 C 1 (Inner Corridor grading caps and four findings) and §6 B 1 (Outer Corridor doubled caps). Landform Grading Manual referenced as adopted by the City of Los Angeles Planning Commission.
Working on a property in the Mulholland Specific Plan area?
Design 1 Studio reviews zoning, slope, visibility, grading, and plan check constraints before drawings move too far in the wrong direction.
Building design firm based in Pasadena, California. Over a decade serving Los Angeles County with residential and commercial design, including ADUs, hillside projects, multifamily, and historic-district work. Inspector-led methodology focused on producing drawings that anticipate plan check rather than react to it. Specialty work in Mulholland Specific Plan navigation. Contact through design1.studio.