City of Los Angeles · Mulholland Specific Plan
Stream Protection Buffer
MSPSP §5 B 2
Definition
Streams in the Mulholland Specific Plan area are designated on the Mulholland Topographic / Lot-line map series and may include water courses with surface or subsurface flow that supports or has supported riparian vegetation. The Plan establishes a 100-foot construction and earth-movement buffer measured from either bank.
No project may be constructed within 100 feet of either bank of an identified stream, and no more than 100 cubic yards of earth may be moved within that buffer, without prior Director approval. Approval is conditioned on a biologist’s report and a recorded covenant binding the project to the biologist’s recommendations.
What the Buffer Triggers
- 100-foot construction buffer measured from either stream bank.
- 100-cubic-yard earth movement cap within the buffer absent Director approval.
- Biologist’s report assessing project impacts on the stream and surrounding wildlife.
- Recorded covenant with the County Recorder, in a form satisfactory to the City Attorney, binding the project to the biologist’s recommendations.
- Administrative Review ineligibility — stream proximity within 100 feet is one of the three Plan disqualifiers.
What Plan Check Looks For
- Identification of any stream within 100 feet of project elements, using the Mulholland map series and the topographic survey.
- A Biologist’s Stream/Riparian Report assessing impacts on the stream and surrounding wildlife.
- The recorded covenant, with form approved by the City Attorney.
- Coordination between the Grading Plan and the biologist’s mitigation measures.
- Confirmation that no project elements lie within the buffer absent Director approval.
- Project Compliance routing — stream proximity disqualifies Administrative Review.
Upstream Decisions
- Map identified streams against the project at the schematic stage. The buffer is measured from either bank.
- Where a project is unavoidably within the buffer, retain a biologist early. The biologist’s report shapes mitigation, project geometry, and the recorded covenant — not the other way around.
- Track the 100-cubic-yard earth movement cap separately from the lot-wide grading cap. Both apply.
- Confirm Administrative Review ineligibility in the project description from the start.
The project requires Director approval under §5 B 2: a biologist’s report on impacts to the stream and wildlife, a recorded covenant binding the project to the biologist’s recommendations, and demonstration of consistency with the surrounding ecology. The project is not eligible for Administrative Review and routes to Project Compliance with the DRB regardless of cumulative square footage.
Source: Mulholland Scenic Parkway Specific Plan, §5 B 2 (Streams). Stream identification per the Mulholland Topographic / Lot-line map series adopted as part of the Specific Plan.
Working on a property in the Mulholland Specific Plan area?
Design 1 Studio reviews zoning, slope, visibility, grading, and plan check constraints before drawings move too far in the wrong direction.
Building design firm based in Pasadena, California. Over a decade serving Los Angeles County with residential and commercial design, including ADUs, hillside projects, multifamily, and historic-district work. Inspector-led methodology focused on producing drawings that anticipate plan check rather than react to it. Specialty work in Mulholland Specific Plan navigation. Contact through design1.studio.